Dates set for BD11.2m sewerage, and road works
TDT | Manama
Email: mail@newsofbahrain.com
More than BD11.2 million worth of sewerage work is being built or readied for the Fourth Constituency in the Northern Governorate, the Ministry of Works has told Parliament, with some schemes running into 2027.
In a written reply to MP Hassan Ebrahim, the ministry said the programme covered sewerage networks, road upgrades and paving, along with follow-up work linked to the Ishbiliya housing project.
It said start dates for some road schemes would depend on completing technical steps, securing funding and gaining clearances from relevant service bodies.
The ministry put the total cost of sewerage projects now under way, and due for completion in 2026 and 2027, at about BD11,228,139.
One of the biggest jobs is in Abu Quwwa, Block 457, where a new sewerage network is being built at a cost of BD5,827,176.
Work began in May 2025 and the ministry expects it to finish in the fourth quarter of 2027.
Progress stands at 9.5 per cent, it said. The scheme includes one pumping station and about 23-kilometre long of sewer lines.