*** ----> Sanad sewerage network achieves 76pc progress | THE DAILY TRIBUNE | KINGDOM OF BAHRAIN

Sanad sewerage network achieves 76pc progress

ManamaThe Sanitary Engineering Planning and Projects Director of the Ministry of Works, Municipalities Affairs and Urban Planning Eng. Nazha Abu Hindi has revealed that the Ministry has achieved 76 per cent progress on the sewerage network in Sanad, Block 745.

article-image

According to Abu Hindi, the Ministry managed to extend 1100m of main and sub-connections, constructed 57 inspection chambers and connected 31 houses to the network.

The project comprises of extending 827m long main connections, 566m long sub-connections, constructing 100 inspection chambers and connecting 90 houses and real estates to the network. The BD233,251 project was earlier awarded to Tylos Excavations Company.